Bridges24D00193

CONSTRUCTION OF LUKUTANG MALAKI BRIDGE 2, MONTALBAN, RIZAL

CONSTRUCTION OF LUKUTANG MALAKI BRIDGE 2, MONTALBAN, RIZAL is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱57,912,582.42. Status: Past target date (DPWH On-Going). Contractor on record: G F FABIAN CONST. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱57,912,582.42

Progress

Past target date (DPWH On-Going)

Start Date

March 6, 2025

Target End

October 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.