Flood Control and Drainage25DN0102

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, PUROK 5, ZONE 8, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, PUROK 5, ZONE 8, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱4,751,999.09. Status: Past target date (DPWH On-Going). Contractor on record: H FRANCISCO CONST AND SUPPLY. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Cupang River (Downstream), Phase 4, Barangay Cupang, Antipolo City, Rizal
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Rizal 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,751,999.09

Progress

Past target date (DPWH On-Going)

Start Date

May 29, 2025

Target End

August 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.