Roads18CE0051

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0135+000 - K0135+545, K0138+000 - K0138+350, K0141+000 - K0141+529, K0142+179 - K0142+315

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0135+000 - K0135+545, K0138+000 - K0138+350, K0141+000 - K0141+529, K0142+179 - K0142+315 is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱11,662,567.79. Status: Reported complete (DPWH). Contractor on record: WIZARD CONCRETE SOLUTIONS AND CONST CORP FORMERLY: WIZARD TRADING. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-LGRCB-18-0019535 · ₱17,900,000 · release to the district office, not itemized per project

    Possible match · score 0.80

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18CE0051 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-03-20 → 2025-10-20

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (preventive maintenance / overlay)

₱7,476,005 per km= 0.3x the Region III median (n=352)

Contract cost ₱11,662,568 ÷ 1.56 km read from the DPWH title (“K0135+000 - K0135+545; K0138+000 - K0138+350; K0141+000 - K0141+529; K0142+179 - K0142+315”; K-post / station range length). National percentile: 5. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0135+000 - K0135+545, K0138+000 - K0138+350, K0141+000 - K0141+529, K0142+179 - K0142+315

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Slope Protection with Steel Sheet Pile along Talavera River, Brgy. Maestrang Kikay, Talavera, Nueva Ecija
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-18-0019535

₱17,900,000.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

210 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, MERCED

Region V, Region V

2024₱144.6M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS, BALER-DAANG MAHARLIKA (LZ), PROVINCE OF NUEVA ECIJA

Region III, Region III

2021₱101.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROADS, PANTABANGAN-CANILI-BASAL-BALER ROAD, PROVINCE OF NUEVA ECIJA

Region III, Region III

2021₱98.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF P-5 BORABOD TO AWITAN ROAD, DA

Region V, Region V

2023₱96.5M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT PALESTINA, SAN JOSE CITY, NUEVA ECIJA

Nueva Ecija 1st DEO, Region III

2019₱96.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0166+005 - K0166+662, K0135+551.60 - K0135+628, K0137+000 - K0137+386, K0143+304 - K0143+438, K0149+000 - K0149+427, K0149+442 - K0150+446, K0155+080

Nueva Ecija 1st DEO, Region III

2019₱96.1M
Reported complete (DPWH)
View all 210 projects →

4. Implementation

Contract Amount

₱11,662,567.79

Progress

Reported complete (DPWH)

Start Date

May 10, 2018

Target End

September 8, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.