Buildings and Facilities16CJ0059

CONSTRUCTION OF 2 STOREY, 4 CL SB AT NAMBALAN NHS, STA IGNACIA, TARLAC

CONSTRUCTION OF 2 STOREY, 4 CL SB AT NAMBALAN NHS, STA IGNACIA, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱6,138,809.27. Status: Reported complete (DPWH). Contractor on record: ROYAL CROWN MONARCH CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-16-0038894

₱5,140,000.00 · FY2016

Released to Culion Sani (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

328 projects · ₱20.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF PAMPANGA

Region III, Region III

2023₱228.7M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, MANGATAREM-STA CRUZ ROAD, PACKAGE 2, PANGASINAN

Region I, Region I

2018₱188.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS AND DECLARED TOURISM DESTINATIONS, CONCRETING OF ROAD FROM LINGAYEN BAYWALK TO BINMALEY, PANGASINAN

Region I, Region I

2016₱185.6M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 2, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 3, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 1, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
View all 328 projects →

4. Implementation

Contract Amount

₱6,138,809.27

Progress

Reported complete (DPWH)

Start Date

June 16, 2016

Target End

October 13, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.