Unprogrammed Appropriations 202424M00319

CONSTRUCTION OF ROAD, STA 0+000 - STA 1+200, BARANGAY SOLON, SULTAN MASTURA, MAGUINDANAO DEL NORTE

CONSTRUCTION OF ROAD, STA 0+000 - STA 1+200, BARANGAY SOLON, SULTAN MASTURA, MAGUINDANAO DEL NORTE is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱18,720,828.46. Status: Past target date (DPWH On-Going). Contractor on record: MUST ENT. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,720,828.46

Progress

Past target date (DPWH On-Going)

Start Date

August 5, 2025

Target End

November 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.