Construction of Flood Mitigation Structure24A00192

Construction of Flood Mitigation Structure along Bued River-Angalacan River, Barangay Imelda-San Roque, San Jacinto, Pangasinan

Construction of Flood Mitigation Structure along Bued River-Angalacan River, Barangay Imelda-San Roque, San Jacinto, Pangasinan is a DPWH-tracked public work in SAN JACINTO (PANGASINAN), PANGASINAN, Region I. Reported contract value: ₱96,499,268.66. Status: Reported complete (DPWH). Contractor on record: BET CONST & SUPPLY. Figures trace to sumbong.

SAN JACINTO (PANGASINAN), PANGASINAN, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sinucalan River, Barangay San Jose, Urdaneta City, Pangasinan ( Package 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007432

₱1,789,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0004506

₱704,228.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0004505

₱7,662,373.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0000223

₱156,514.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0001610

₱61,365.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007433

₱165,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,268.66

Progress

Reported complete (DPWH)

Start Date

February 26, 2024

Target End

December 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.