Construction of Slope Protection Structure22CK0077

Construction of Slope Protection Structure, Sacobia-Bamban River, Left Bank, Brgy. San Francisco, Concepcion, Tarlac

Construction of Slope Protection Structure, Sacobia-Bamban River, Left Bank, Brgy. San Francisco, Concepcion, Tarlac is a DPWH-tracked public work in CONCEPCION (TARLAC), TARLAC, Region III. Reported contract value: ₱93,169,679.22. Status: Reported complete (DPWH). Contractor on record: FERDSTAR BUILDERS INC. Figures trace to sumbong.

CONCEPCION (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Camiling River, Left Bank, Pao 3rd-Pao 2nd Section (Package A), Camiling, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002779

₱320,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005156

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002922

₱811,709,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005139

₱71,901.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004769

₱50,540.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004759

₱542,182.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

139 projects · ₱8.9B total · 1 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS-CONSTRUCTION OF RING DIKE WITH PUMPING STATION (PHASE 2 & 4), MACABEBE-MASANTOL, PROVINCE OF PAMPANGA

Region III, Region III

2024₱354.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 3, PROVINCE OF PAMPANGA

Region III, Region III

2020₱193.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ABACAN RIVER, DIKING AND SLOPE PROTECTION WORKS-PHASE 2, MEXICO, PAMPANGA

Region III, Region III

2025₱170.1M
Past target date (DPWH On-Going)
No sat.

PASIG-MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, CONTRACT PACKAGE NO. 4-B, RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 15+700 TO STA. 15+957 (PHASE 2), RIGHT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2022₱148.4M
Reported complete (100% progress, DPWH status On-Going)

Flood Control Works - Diking/Slope Protection of Pasig-Potrero River, Bacolor and Porac, Pampanga

PORAC (PAMPANGA), PAMPANGA, Region III

2023₱144.8M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION), PACKAGE 5, PROVINCE OF PAMPANGA

Region III, Region III

2020₱144.7M
Reported complete (DPWH)
View all 139 projects →

4. Implementation

Contract Amount

₱93,169,679.22

Progress

Reported complete (DPWH)

Start Date

March 26, 2022

Target End

November 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.