Buildings and Facilities24IH0036

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE II, BARANGAY ACEDILLO, VICTORIA, NORTHERN SAMAR

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE II, BARANGAY ACEDILLO, VICTORIA, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱3,685,230.62. Status: Reported complete (DPWH). Contractor on record: FOUR JJ CONST. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Catubig River, Barangay Canuctan, Catubig, Northern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Northern Samar 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

35 projects · ₱320.1M total · 0 flags

4. Implementation

Contract Amount

₱3,685,230.62

Progress

Reported complete (DPWH)

Start Date

February 22, 2024

Target End

July 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.