Construction of Flood Mitigation Structure23CF0092

Construction of Flood Control Structure (Gabion) along Digmala River, Barangay Ariendo, Bongabon, Nueva Ecija

Construction of Flood Control Structure (Gabion) along Digmala River, Barangay Ariendo, Bongabon, Nueva Ecija is a DPWH-tracked public work in BONGABON (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱88,777,708.23. Status: Reported complete (DPWH). Contractor on record: CELSO C FERRER CONST CORP. Figures trace to sumbong.

BONGABON (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Talavera River, Barangay Bantug, Talavera, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Nueva Ecija 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

205 projects · ₱5.4B total · 3 flags

4. Implementation

Contract Amount

₱88,777,708.23

Progress

Reported complete (DPWH)

Start Date

April 17, 2023

Target End

December 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.