Roads15B00069No coordinates published by DPWH

REHAB./RECONST'N/UPGRADING OF DAMAGED PAVED NAT'L RD. INCLUDING DRAINAGE BASED ON PVM'T MNG'T SYSTEM

REHAB./RECONST'N/UPGRADING OF DAMAGED PAVED NAT'L RD. INCLUDING DRAINAGE BASED ON PVM'T MNG'T SYSTEM is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱28,274,761.84. Status: Reported complete (DPWH). Contractor on record: JERCON TRADE CONST DEVELOPMENT CORP FROMERLY: CAUAYAN UNITED ENT. Figures trace to dpwh.

Region II, Region II

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region II

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

1 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    Not yet linked

  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHAB./RECONST'N/UPGRADING OF DAMAGED PAVED NAT'L RD. INCLUDING DRAINAGE BASED ON PVM'T MNG'T SYSTEM

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

36 projects · ₱437.7M total · 0 flags

Other projects by this contractor

View all 36 projects →

4. Implementation

Contract Amount

₱28,274,761.84

Progress

Reported complete (DPWH)

Start Date

February 21, 2016

Target End

August 18, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.