GAA 2024 SSP24EE0129

PACKAGE IV-CONSTRUCTION OF MULTI-PURPOSE BUILDING & DOJ BUILDING:1. BRGY. MENDOZA, ROXAS2. BRGY. CASIAN, TAYTAY3. PALAWAN STATE UNIVERSITY LINAPACAN CAMPUS, LINAPACAN4. BARANGAY TURDA, CORON5. PALAWAN STATE UNIVERSITY TAYTAY CAMPUS, TAYTAY6. B

PACKAGE IV-CONSTRUCTION OF MULTI-PURPOSE BUILDING & DOJ BUILDING:1. BRGY. MENDOZA, ROXAS2. BRGY. CASIAN, TAYTAY3. PALAWAN STATE UNIVERSITY LINAPACAN CAMPUS, LINAPACAN4. BARANGAY TURDA, CORON5. PALAWAN STATE UNIVERSITY TAYTAY CAMPUS, TAYTAY6. B is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱56,858,017.10. Status: Past target date (DPWH On-Going). Contractor on record: FUTURISTIC TRADING. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Sitio Butterfly, Barangay Quinlogan, Quezon, Palawan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Palawan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱56,858,017.10

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2024

Target End

April 7, 2025

5. Audit