Roads17NI0023

REHB/RECONS OF NATL RD W SLIPS,SLOPE COLLPSE & LNDSLIDE 2NDRY,SURIGAO-DVO CSTAL RD-K1453+430-K1453+456.2,K1453+706.80 K1453+722.50, K1453+893K1453+930,K1465+384K1465+486,K1476+677.50 K1476+891,K1478+643-K1478+673.30,K1500+550-K1500+580,K1506+311-K1506+329

REHB/RECONS OF NATL RD W SLIPS,SLOPE COLLPSE & LNDSLIDE 2NDRY,SURIGAO-DVO CSTAL RD-K1453+430-K1453+456.2,K1453+706.80 K1453+722.50, K1453+893K1453+930,K1465+384K1465+486,K1476+677.50 K1476+891,K1478+643-K1478+673.30,K1500+550-K1500+580,K1506+311-K1506+329 is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱42,002,574.85. Status: Reported complete (DPWH). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱31,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Mangagoy River, Mangagoy, Bislig City, Surigao del Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-17-0008721

₱-12,000,000.00 · FY2017

Released to Zamboanga Sibugay Is 2nd District Engineering Offic (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱17.1B total · 2 flags

4. Implementation

Contract Amount

₱42,002,574.85

Progress

Reported complete (DPWH)

Start Date

May 4, 2017

Target End

January 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.