Buildings and Facilities16DF0197

CONSTRUCTION OF CLASSROOMS-CONSTRUCTION OF 4STY 8CL SCHOOL BUILDING AT SAN JOSE COMMUNITY HS, GEN. M

CONSTRUCTION OF CLASSROOMS-CONSTRUCTION OF 4STY 8CL SCHOOL BUILDING AT SAN JOSE COMMUNITY HS, GEN. M is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱14,460,570.17. Status: Reported complete (DPWH). Contractor on record: OMNICON BUILDERS. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2016 · ₱20,000

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-16-0027749 · ₱8,540,498

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Unit-cost benchmark · School building, cost per classroom (new school building)

₱1,807,571 per classroom= 0.8x the Region IV-A median (n=665)

Contract cost ₱14,460,570 ÷ 8 classroom read from the DPWH title (“4STY 8CL”; classroom count in title). National percentile: 54. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Canas River, Brgys. Tapia Section, Pinagtipunan, San Juan II Section and Tejero Section, Gen. Trias, Cavite 6th LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0027749

₱8,540,498.00 · FY2016

Released to Division of Sorsogon (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,460,570.17

Progress

Reported complete (DPWH)

Start Date

October 26, 2016

Target End

April 23, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.