Roads19EH0004

PREVENTIVE MAINTENANCE (SECONDARY ROADS) - SIBUYAN CIRCUMFERENTIAL ROAD,K0087 + 420 - K0087 + 960 (ACTUAL & RBIA), SIBUYAN ISLAND, ROMBLON

PREVENTIVE MAINTENANCE (SECONDARY ROADS) - SIBUYAN CIRCUMFERENTIAL ROAD,K0087 + 420 - K0087 + 960 (ACTUAL & RBIA), SIBUYAN ISLAND, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱8,368,326.16. Status: Reported complete (DPWH). Contractor on record: MT GUITING-GUITING CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-19-0004305

₱545,008.00 · FY2019

Released to Rajah Soliman Science and Technology High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Preventive Maintenance (Secondary Roads)

₱8,368,326.16 · MT. GUITING-GUITING CONST.

4. Implementation

Contract Amount

₱8,368,326.16

Progress

Reported complete (DPWH)

Start Date

July 2, 2019

Target End

September 22, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.