Roads20L00156

CONSTRUCTION OF BRIDGE APPROACH - DAVAO CITY COASTAL BYPASS ROAD (BAGO APLAYA - TIMES BEACH - ROXAS AVENUE), PACKAGE 4A, DAVAO CITY

CONSTRUCTION OF BRIDGE APPROACH - DAVAO CITY COASTAL BYPASS ROAD (BAGO APLAYA - TIMES BEACH - ROXAS AVENUE), PACKAGE 4A, DAVAO CITY is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱361,811,693.78. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

546 projects · ₱133.2B total · 0 flags

4. Implementation

Contract Amount

₱361,811,693.78

Progress

Reported complete (DPWH)

Start Date

January 3, 2021

Target End

November 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.