Construction of Flood Mitigation Structure24AA0206

Construction of Flood Control Structure, Barangay Teppang, Bacarra, Ilocos Norte

Construction of Flood Control Structure, Barangay Teppang, Bacarra, Ilocos Norte is a DPWH-tracked public work in BACARRA (ILOCOS NORTE), ILOCOS NORTE, Region I. Reported contract value: ₱9,799,416.20. Status: Reported complete (DPWH). Contractor on record: BJMJB CONST & SUPPLY. Figures trace to sumbong.

BACARRA (ILOCOS NORTE), ILOCOS NORTE, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Teppang, Bacarra, Ilocos Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007417

₱1,862,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0000354

₱849,963.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007418

₱172,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

37 projects · ₱803.6M total · 26 flags

4. Implementation

Contract Amount

₱9,799,416.20

Progress

Reported complete (DPWH)

Start Date

February 13, 2024

Target End

May 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.