DPWH reports: Completed · 100%

Open DPWH portal record ↗

Publicly reported (according to cited sources)

  • Office of the Ombudsman (charges, as reported at Senate Blue Ribbon/DOJ update) · 2026-01-19

    “Discaya last month was charged with graft and malversation in connection with a P96.5-million alleged ghost flood control project in Davao Occidental”
    Source link (external) ↗
  • DPWH Sec. Vince Dizon (criminal complaint to Ombudsman) · 2025-10-23

    “The Davao Occidental project was never completed... So it is clearly a ghost project”
    Source link (external) ↗

Publicly reported by the cited sources; not a finding by this site. Criminal or administrative charges, where cited, are described as pending unless the source states a final judgment. Right of reply / submit evidence

Construction of Revetment22LE0029

Construction of Concrete Revetment, Culaman, Sta. 0+000 - Sta. 2+000, Jose Abad Santos, Davao Occidental

Construction of Concrete Revetment, Culaman, Sta. 0+000 - Sta. 2+000, Jose Abad Santos, Davao Occidental is a DPWH-tracked public work in JOSE ABAD SANTOS (TRINIDAD) (DAVAO OCCIDENTAL), DAVAO OCCIDENTAL, Region XI. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: ST TIMOTHY CONST CORP. Figures trace to sumbong.

JOSE ABAD SANTOS (TRINIDAD) (DAVAO OCCIDENTAL), DAVAO OCCIDENTAL, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Revetment/Dike or Flood Control (Phase1) along the Existing Bridge Connecting Barangay North Lamidan and Barangay South Lamidan, Davao Occidental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003155

₱150,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003042

₱3,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0008209

₱84,099.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0005354

₱78,062.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0006988

₱73,277.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

942 projects · ₱44.1B total · 42 flags

Other projects by this contractor

No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, MANILA NORTH RD - K0578+640 - K0578+900 R/S

Region I, Region I

2023₱390.8M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 1), ORION, BATAA

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD AND CAUSEWAY FOR TOURISM ALONG AZAGRA PORT, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1

Region IV-B, Region IV-B

2022₱289.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CAJIDIOCAN PORT, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG POBLACION SAN FERNANDO, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
View all 942 projects →

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

October 2, 2022

5. Audit