Flood Control and Drainage19JI0060

CONSTRUCTION OF FLOOD CONTROL FOR PREVENTION AND MITIGATION ALONG SIBUGUEY RIVER, BRGY. BALUGO-BRGY. POBLACION, IMELDA, ZAMBOANGA SIBUGAY, STA. 0+000.00 - STA. 0+304.50

CONSTRUCTION OF FLOOD CONTROL FOR PREVENTION AND MITIGATION ALONG SIBUGUEY RIVER, BRGY. BALUGO-BRGY. POBLACION, IMELDA, ZAMBOANGA SIBUGAY, STA. 0+000.00 - STA. 0+304.50 is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱33,380,220.00. Status: Reported complete (DPWH). Contractor on record: BARILLO CONST AND ENT. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIX-19-0000701

₱5,949,000.00 · FY2019

Released to Zamboanga Sibugay National High Schoo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

140 projects · ₱2.5B total · 0 flags

Other projects by this contractor

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION/IMPROVEMENT OF FLOOD CONTROL FOR PREVENTION AND MITIGATION ALONG BRGY. SAN JOSE-POBLACION IMELDA, PART OF SIBUGUEY RIVER, IMELDA, Z

Region IX, Region IX

2019₱112.1M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG KABASALAN RIVER (PHASE III), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2021₱105.1M
Reported complete (DPWH)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE IV), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2022₱104.9M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱104.8M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 2

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)
View all 140 projects →

4. Implementation

Contract Amount

₱33,380,220.00

Progress

Reported complete (DPWH)

Start Date

October 13, 2019

Target End

July 15, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.