Flood Control and Drainage25RG0158

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG SITIO BLISS, BARANGAY POBLACION, BI

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG SITIO BLISS, BARANGAY POBLACION, BI is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱28,949,000.00. Status: Past target date (DPWH On-Going). Contractor on record: MIGHTY HOK SUMMIT CONST. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Satellite images pending: this project is in the imagery queue (completed projects first, then ongoing). Before/after images will appear here when it is processed.

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱17,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25RG0158 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    43% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Negros Oriental

Based on the coordinates published with the DPWH record and NOAH file NegrosOriental.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG SITIO BLISS, BARANGAY POBLACION, BI

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱17,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Tinaogan, Bindoy, Negros Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Negros Oriental 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

91 projects · ₱3.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING : PRIMARY ROADS: DUMAGUETE SOUTH RD - K0059 + 610 - K0061 + 813, SIATON, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2025₱116.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: CONSTRUCTION OF CONCRETE ROAD - CROSSING ARCO ROAD LEADING TO FOREST CONSERVATION AND REHABILITATION ECO-TOURISM SITE (KABULAKAN

Negros Oriental 3rd DEO, Negros Island Region

2021₱101.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING - PRIMARY ROADS: DUMAGUETE SOUTH RD - K0046 + 025 - K0048 + 740, SIATON, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2022₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD AT HAGDAN PROPER, B

Cebu 2nd DEO, Region VII

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING - PRIMARY ROADS: DUMAGUETE SOUTH RD - K0048 + 817 - K0050 + 910, SIATON, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2023₱91.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING - PRIMARY ROADS- DUMAGUETE NORTH RD. (JCT. BAIS-KABANKALAN-NEGROS OCC BDRY) - K0120+300 - K0121+820, GUIHULNGAN CITY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱84.6M
Past target date (DPWH On-Going)
View all 91 projects →

4. Implementation

Contract Amount

₱28,949,000.00

Progress

Past target date (DPWH On-Going)

Start Date

July 7, 2025

Target End

January 24, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.