Construction of Flood Mitigation Structure23OE0051

Construction of Retarding Basin at Estero de Maypajo, (Phase II), Tondo, Manila

Construction of Retarding Basin at Estero de Maypajo, (Phase II), Tondo, Manila is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱34,298,030.64. Status: Reported complete (DPWH). Contractor on record: G F FABIAN CONST. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,343,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure, Easement Road Estero de Pandacan (Tripa de Gallina - P. Quirino Ave.) Manila
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

North Manila District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱34,298,030.64

Progress

Reported complete (DPWH)

Start Date

February 13, 2023

Target End

January 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.