Construction of Flood Mitigation Structure22CC0257

Construction of Flood Control Structure and Improvement of Waterways at Brgy. Piel, Baliuag, Bulacan

Construction of Flood Control Structure and Improvement of Waterways at Brgy. Piel, Baliuag, Bulacan is a DPWH-tracked public work in CITY OF BALIUAG (BULACAN), BULACAN, Region III. Reported contract value: ₱48,999,769.37. Status: Reported complete (DPWH). Contractor on record: ST MATTHEW GEN CONTRACTOR & DEVELOPMENT CORP. Figures trace to sumbong.

CITY OF BALIUAG (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure and Improvement of Waterways at Brgy. Piel, Baliuag, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002958

₱2,583,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002898

₱71,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0000929

₱84,820.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22CC0257-Construction of Flood Control Structure

₱47,284,322.35 · ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT .

Contractor

61 projects · ₱4.8B total · 15 flags

4. Implementation

Contract Amount

₱48,999,769.37

Progress

Reported complete (DPWH)

Start Date

April 5, 2022

Target End

January 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.