Flood Control and Drainage20FB0037

FLOOD CONTROL STRUCTURES/FACILITIES: CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG PUROK 2, RAWIS, LEGAZPI CITY (PHASE 2)

FLOOD CONTROL STRUCTURES/FACILITIES: CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG PUROK 2, RAWIS, LEGAZPI CITY (PHASE 2) is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱48,984,919.40. Status: Reported complete (DPWH). Contractor on record: PROTECH CONST & DEVELOPMENT CORP FORMERLY. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱50,000

    Probable match · score 0.90

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱47,535,183 · LOURBEL CONSTRUCTION & SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-12-29 → 2023-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Medium flood hazard · Albay

Based on the coordinates published with the DPWH record and NOAH file Albay.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: FLOOD CONTROL STRUCTURES/FACILITIES: CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG PUROK 2, RAWIS, LEGAZPI CITY (PHASE 2)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation System, Along Purok 2, Rawis, Legaspi City (Phase 2)
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Albay 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Const. of FC along Purok 2, Rawis, Leg. City

₱47,535,183.17 · LOURBEL CONSTRUCTION & SUPPLY

Award / contract ref: 20FB0037

4. Implementation

Contract Amount

₱48,984,919.40

Progress

Reported complete (DPWH)

Start Date

February 7, 2020

Target End

October 3, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.