Roads24K00486

CLUSTER A PREVENTIVE MAINTENANCE OF VARIOUS ROAD PROJECTS IN LANAO DEL NORTE1) MALABANG-DOBLESTON-TUKURAN RD - K1970 + 749 - K1971 + 274=PHP 24,404,850.002) MALABANG-DOBLESTON-TUKURAN RD - K1972 + 570 - K1973 + 000

CLUSTER A PREVENTIVE MAINTENANCE OF VARIOUS ROAD PROJECTS IN LANAO DEL NORTE1) MALABANG-DOBLESTON-TUKURAN RD - K1970 + 749 - K1971 + 274=PHP 24,404,850.002) MALABANG-DOBLESTON-TUKURAN RD - K1972 + 570 - K1973 + 000 is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱113,859,766.19. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LANAO BUILDER AND ENT. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱113,859,766.19

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

October 21, 2024

Target End

March 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.