Construction of Flood Mitigation Structure23HB0068

Construction of Flood Control Structure along Wahig River, Sierra Bullones, Bohol

Construction of Flood Control Structure along Wahig River, Sierra Bullones, Bohol is a DPWH-tracked public work in SIERRA BULLONES (BOHOL), BOHOL, Region VII. Reported contract value: ₱98,999,836.90. Status: Reported complete (DPWH). Contractor on record: CLAIRE CONST AND SUPPLY CORP / MUANA CONST AND DEVELOPMENT CORP FORMERLY. Figures trace to sumbong.

SIERRA BULLONES (BOHOL), BOHOL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure and Drainage System of Cantomimbo Flood Control, Balilihan, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bohol 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱98,999,836.90

Progress

Reported complete (DPWH)

Start Date

April 25, 2023

Target End

May 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.