Bridges22AA0043

WIDENING OF PERMANENT BRIDGES - PANCIAN BR. (B00549LZ) ALONG MANILA NORTH ROAD

WIDENING OF PERMANENT BRIDGES - PANCIAN BR. (B00549LZ) ALONG MANILA NORTH ROAD is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱35,279,949.79. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR & DEVELOPMENT CORP FORMERLY:ST GERRARD CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2022 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22AA0043 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-01-18 → 2025-05-14

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: WIDENING OF PERMANENT BRIDGES - PANCIAN BR. (B00549LZ) ALONG MANILA NORTH ROAD

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Dike along Kabuayan Creek, Burgos, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

103 projects · ₱10.5B total · 4 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF THE NBI MAIN BUILDING (PHASE I)

National Capital Region, National Capital Region

2023₱447.7M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURES AL;ONG PUERTO PRINCESA SDOUTH ROAD, K0147+398-K0180+313 (WITH EXCEPTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURE ALONG PUERTO PRINCESA SOUTH ROAD- K0180+313-K0203+730 (INTERMITTENT SECTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, PRIMARY ROADS, DAANG MAHARLIKA (LZ), NUEVA ECIJA 2ND LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA

Region III, Region III

2017₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 1: 1. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF PALO - PASTRANA - STA. FE BY-PASS RD, PACKAGE A 2. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATION

Region VIII, Region VIII

2025₱289.4M
Ongoing (DPWH-reported)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: CONSTRUCTION OF MISSING LINKS/NEW ROADS -TUGUEGARAO CITY BOULEVARD (PINACANAUAN BRIDGE 2 AND APPROACHES), PHASE 2

Region II, Region II

2023₱285.9M
Past target date (DPWH On-Going)
View all 103 projects →

4. Implementation

Contract Amount

₱35,279,949.79

Progress

Reported complete (DPWH)

Start Date

February 18, 2022

Target End

May 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.