Flood Control and Drainage19IA0019

RECONSTRUCTION OF BALAQUID FLOOD CONTROL STRUCTURES ALONG BILIRAN CIRCUMFERENTIAL ROAD, CABUCGAYAN, BILIRAN (124.537194°, 11.477034° TO 124.537040°, 11.377889°)

RECONSTRUCTION OF BALAQUID FLOOD CONTROL STRUCTURES ALONG BILIRAN CIRCUMFERENTIAL ROAD, CABUCGAYAN, BILIRAN (124.537194°, 11.477034° TO 124.537040°, 11.377889°) is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱28,486,800.00. Status: Reported complete (DPWH). Contractor on record: CHUCON BUILDERS CORP FORMERLY: CHU CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-BMB-D-19-0021677 · ₱42,041,886 · release to the district office, not itemized per project

    Possible match · score 0.71

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱28,486,800 · CHU CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-03-28 → 2025-04-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Biliran

Based on the coordinates published with the DPWH record and NOAH file Biliran.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: RECONSTRUCTION OF BALAQUID FLOOD CONTROL STRUCTURES ALONG BILIRAN CIRCUMFERENTIAL            ROAD, CABUCGAYAN, BILIRAN (124.537194°, 11.477034° TO 124.537040°, 11.377889°)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-19-0021677

₱42,041,886.00 · FY2019

Released to General Headquarters - Proper (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

19IA0019 Reconstruction of Balaquid Flood Control

₱28,486,800.00 · CHU CONSTRUCTION

Award / contract ref: 19IA0019

Contractor

103 projects · ₱3.2B total · 1 flags

4. Implementation

Contract Amount

₱28,486,800.00

Progress

Reported complete (DPWH)

Start Date

July 4, 2019

Target End

December 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.