Roads16A00025No coordinates published by DPWH

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS, CANDON-SANTIAGO-SAN ESTEBAN COASTAL ROAD LEADING TO SANTIAGO COVE, SANTIAGO, ILOCOS SUR

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS, CANDON-SANTIAGO-SAN ESTEBAN COASTAL ROAD LEADING TO SANTIAGO COVE, SANTIAGO, ILOCOS SUR is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱92,869,059.37. Status: Reported complete (DPWH). Contractor on record: WERR CORP INTERNATIONAL. Figures trace to dpwh.

Region I, Region I

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region I

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 16A00025 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS, CANDON-SANTIAGO-SAN ESTEBAN COASTAL ROAD LEADING TO SANTIAGO COVE, SANTIAGO, ILOCOS SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

114 projects · ₱5.3B total · 0 flags

4. Implementation

Contract Amount

₱92,869,059.37

Progress

Reported complete (DPWH)

Start Date

March 28, 2016

Target End

September 4, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.