Unprogrammed Appropriations 202424BD0230

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BASI FLOOD CONTROL SYSTEM, PACKAGE 1, BASI, SOLANA, CAGAYAN

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BASI FLOOD CONTROL SYSTEM, PACKAGE 1, BASI, SOLANA, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱95,535,134.84. Status: Past target date (DPWH On-Going). Contractor on record: A M ORETA & CO INC 108. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Management Projects, Centro, Amulung, Cagayan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cagayan 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱95,535,134.84

Progress

Past target date (DPWH On-Going)

Start Date

June 10, 2025

Target End

May 6, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.