Flood Control and Drainage21BF0069

CONSTRUCTION OF FLOOD CONTROL PROJECT, BARANGAY EDEN, MUNICIPALITY OF SAN MANUEL, ISABELA

CONSTRUCTION OF FLOOD CONTROL PROJECT, BARANGAY EDEN, MUNICIPALITY OF SAN MANUEL, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱24,007,479.36. Status: Reported complete (DPWH). Contractor on record: RR BUILDERS. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control project, Barangay Eden, Municipality of San Manuel, Isabela
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Isabela 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

55 projects · ₱644.8M total · 0 flags

Other projects by this contractor

No sat.

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL STRUCTURE (CULLALABO SUR SECTION), BARANGAY CULLALABO, BURGOS, ISABELA

Isabela 2nd DEO, Region II

2025₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURESAND DRAINAGE SYSTEMS - CONSTRUCTION OF MALACOPA CREEK RIVER FLOOD CONTROL PROJECT ALONG PRESIDENT BRIDGE (UPSTREAM SECTION) BARANGAY DALIG-KALINGA, AURORA, ISABELA

Isabela 2nd DEO, Region II

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF HALL OF JUSTICE, BARANGAY RIZAL, ROXAS, ISABELA

Isabela 2nd DEO, Region II

2024₱48.9M
Past target date (DPWH On-Going)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLICBUILDINGS/ FACILITIES - CONSTRUCTION OF SANTA CRUZ - CAGURUNGAN EDEN ROAD, SAN MANUEL, ISABELA STA. 0+000 TO 1+330, CONSTRU

Isabela 2nd DEO, Region II

2025₱24.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF STANDARD TWO-STOREY 10 CLASSROOM SCHOOL BUILDING, MUÑOZ HIGH SCHOOL, ROXAS, ISABELA

Isabela 2nd DEO, Region II

2019₱20.0M
Reported complete (DPWH)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES- CONSTRUCTION OF BRGY. BAGNOS TO BRGY. ESPERANZA EAST ROAD, AURORA, ISABELA

Isabela 2nd DEO, Region II

2022₱19.5M
Reported complete (DPWH)
View all 55 projects →

4. Implementation

Contract Amount

₱24,007,479.36

Progress

Reported complete (DPWH)

Start Date

January 10, 2022

Target End

August 3, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.