Buildings and Facilities19BF0120

CONSTRUCTION OF STANDARD TWO-STOREY 10 CLASSROOM SCHOOL BUILDING, MUÑOZ HIGH SCHOOL, ROXAS, ISABELA

CONSTRUCTION OF STANDARD TWO-STOREY 10 CLASSROOM SCHOOL BUILDING, MUÑOZ HIGH SCHOOL, ROXAS, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱20,014,645.54. Status: Reported complete (DPWH). Contractor on record: RR BUILDERS. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-19-0010322

₱-12,066,096.00 · FY2019

Released to Abra District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

55 projects · ₱644.8M total · 0 flags

Other projects by this contractor

No sat.

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL STRUCTURE (CULLALABO SUR SECTION), BARANGAY CULLALABO, BURGOS, ISABELA

Isabela 2nd DEO, Region II

2025₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURESAND DRAINAGE SYSTEMS - CONSTRUCTION OF MALACOPA CREEK RIVER FLOOD CONTROL PROJECT ALONG PRESIDENT BRIDGE (UPSTREAM SECTION) BARANGAY DALIG-KALINGA, AURORA, ISABELA

Isabela 2nd DEO, Region II

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF HALL OF JUSTICE, BARANGAY RIZAL, ROXAS, ISABELA

Isabela 2nd DEO, Region II

2024₱48.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL PROJECT, BARANGAY EDEN, MUNICIPALITY OF SAN MANUEL, ISABELA

Isabela 2nd DEO, Region II

2021₱24.0M
Reported complete (DPWH)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLICBUILDINGS/ FACILITIES - CONSTRUCTION OF SANTA CRUZ - CAGURUNGAN EDEN ROAD, SAN MANUEL, ISABELA STA. 0+000 TO 1+330, CONSTRU

Isabela 2nd DEO, Region II

2025₱24.0M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES- CONSTRUCTION OF BRGY. BAGNOS TO BRGY. ESPERANZA EAST ROAD, AURORA, ISABELA

Isabela 2nd DEO, Region II

2022₱19.5M
Reported complete (DPWH)
View all 55 projects →

4. Implementation

Contract Amount

₱20,014,645.54

Progress

Reported complete (DPWH)

Start Date

November 25, 2019

Target End

September 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.