Buildings and Facilities19HB0199

CONSTRUCTION AND COMPLETION OF 1-STOREY, 2 CLASSROOMS OMJON ELEMENTARY SCHOOL, VALENCIA, BOHOL

CONSTRUCTION AND COMPLETION OF 1-STOREY, 2 CLASSROOMS OMJON ELEMENTARY SCHOOL, VALENCIA, BOHOL is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱4,238,124.27. Status: Reported complete (DPWH). Contractor on record: ZET CONST. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0011352

₱9,308,000.00 · FY2019

Released to Sikatuna National Agricultural High Sch (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,238,124.27

Progress

Reported complete (DPWH)

Start Date

September 24, 2019

Target End

March 1, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.