Roads18CA0058

NETWORK DEVELOPMENT PROGRAM-ROAD-WIDENING-PRIMARY ROADS-JOSE ABAD SANTOS AVENUE (JASA) K0105+874.00 - K0106+335.00, K0109+640- K0109+831.60, K0112+412.25 - K0112+658.00, K0113+268.00 - K0113+460.00, K0113+995- K0114+471.00, K0114+714.50 - K0114+854

NETWORK DEVELOPMENT PROGRAM-ROAD-WIDENING-PRIMARY ROADS-JOSE ABAD SANTOS AVENUE (JASA) K0105+874.00 - K0106+335.00, K0109+640- K0109+831.60, K0112+412.25 - K0112+658.00, K0113+268.00 - K0113+460.00, K0113+995- K0114+471.00, K0114+714.50 - K0114+854 is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱52,148,599.75. Status: Reported complete (DPWH). Contractor on record: SUPREME BUILDERS CONST AND TRADING. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Concrete Revetment, Sapang Gila Tributary to Almacen, Bataan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0014605

₱0.00 · FY2018

Released to Division of Bataan (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

71 projects · ₱1.5B total · 0 flags

4. Implementation

Contract Amount

₱52,148,599.75

Progress

Reported complete (DPWH)

Start Date

May 23, 2018

Target End

June 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.