Rehabilitation / Major Repair of Drainage Structure23DO0054

Rehabilitation of Drainage System at Lorenzo Compound, Barangay Guitnang Bayan II, San Mateo, Rizal

Rehabilitation of Drainage System at Lorenzo Compound, Barangay Guitnang Bayan II, San Mateo, Rizal is a DPWH-tracked public work in SAN MATEO (RIZAL), RIZAL, Region IV-A. Reported contract value: ₱4,750,931.77. Status: Reported complete (DPWH). Contractor on record: T REYES CONST. Figures trace to sumbong.

SAN MATEO (RIZAL), RIZAL, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure, Barangay Maly, San Mateo, Rizal
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Rizal 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,750,931.77

Progress

Reported complete (DPWH)

Start Date

April 13, 2023

Target End

September 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.