Bridges15BD0126

REHAB./MAJOR REPAIR OF PERMANENT BRIDGES, PANGUL BRIDGE ALONG CAGAYAN-APAYAO ROAD, SOLANA, CAGAYAN

REHAB./MAJOR REPAIR OF PERMANENT BRIDGES, PANGUL BRIDGE ALONG CAGAYAN-APAYAO ROAD, SOLANA, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱1,957,615.00. Status: Reported complete (DPWH). Contractor on record: DEKM CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System, Caggay, Tuguegarao City, Cagayan 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0012658

₱3,968,267.00 · FY2016

Released to Soccsksargen Centers for Health Development To (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,957,615.00

Progress

Reported complete (DPWH)

Start Date

February 17, 2016

Target End

May 16, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.