Trust Funds 202121LH0162

CONSTRUCTION OF THE FOLLOWING PROJECTS AT BRGY. DALIAON PLANTATION, TORIL DISTRICT, DAVAO CITY, LGSF-BPD, ELCAC (1) REHABILITATION OF WATER SUPPLY SYSTEM AT PUROK 10, BRGY. DALIAON PLANTATION, DAVAO CITY (2) REHABILITATION/IMPROVEMENT OF COVERED COURT AT

CONSTRUCTION OF THE FOLLOWING PROJECTS AT BRGY. DALIAON PLANTATION, TORIL DISTRICT, DAVAO CITY, LGSF-BPD, ELCAC (1) REHABILITATION OF WATER SUPPLY SYSTEM AT PUROK 10, BRGY. DALIAON PLANTATION, DAVAO CITY (2) REHABILITATION/IMPROVEMENT OF COVERED COURT AT is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱19,595,979.07. Status: Reported complete (DPWH). Contractor on record: ZJN DEVELOPMENT CONST. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2021 · ₱25,000

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-02-05 → 2025-09-28

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF THE FOLLOWING PROJECTS AT BRGY. DALIAON PLANTATION, TORIL DISTRICT, DAVAO CITY, LGSF-BPD, ELCAC (1) REHABILITATION OF WATER SUPPLY SYSTEM AT PUROK 10, BRGY. DALIAON PLANTATION, DAVAO CITY (2) REHABILITATION/IMPROVEMENT OF COVERED COURT AT

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction Flood Mitigation Structure protecting Daang Maharlika (MN) at Brgy. Bunawan, Davao City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Davao City 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,595,979.07

Progress

Reported complete (DPWH)

Start Date

September 20, 2022

Target End

February 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.