Flood Control and Drainage19DN0073

CONSTRUCTION OF FLOOD CONTROL STRUCTURES OF CREEK ALONG MARIKINA-INFANTA ROAD, BRGY. DELA PAZ AND BRGY. BAGONG NAYON, ANTIPOLO CITY (FIRST DISTRICT)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES OF CREEK ALONG MARIKINA-INFANTA ROAD, BRGY. DELA PAZ AND BRGY. BAGONG NAYON, ANTIPOLO CITY (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱46,545,100.01. Status: Reported complete (DPWH). Contractor on record: A J LAVA BUILDERS CORP FORMERLY: A J LAVA BUIL. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱46,545,100.01

Progress

Reported complete (DPWH)

Start Date

June 4, 2019

Target End

March 29, 2020