Contractor Concentration (Flood Control)
A contractor holds a very large share of flood-control contract value in a district or province.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP received 38.9% (₱2.39B of ₱6.16B) of recorded flood-control contract value in Romblon District Engineering Office across 73 contracts and 12 contractors, at or above the 25% share threshold (HHI 0.21). This may be due to the contractor's specialized expertise or a lack of other qualified bidders in the area.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Flagged peer group: Romblon District Engineering Office
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Canlumay Flood Control Structure, Odiongan, Romblon24EH0107Flood control | 100% | December 2, 2024 | November 25, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Carmen Shore Protection/Causeway Phase 2, San Agustin, Romblon21EH0053Flood control | 100% | August 31, 2022 | August 8, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along David Bridge Upstream (L/S), Odiongan, Romblon24EH0084Flood control | 100% | February 28, 2025 | November 15, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Mayha River (Phase 2), Odiongan, Romblon24EH0074Flood control | 100% | March 7, 2025 | December 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure, Mayha River Upstream (L/S), Odiongan, Romblon24EH0063Flood control | 100% | February 15, 2025 | December 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure, Sitio Agcahico Brgy.Carmen, San Agustin, Romblon24EH0071Flood control | 100% | February 15, 2025 | November 15, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Show 20 more projects in this bucket
| Construction of Flood Control Structure, Sitio Suong Brgy.Carmen, San Agustin, Romblon24EH0070Flood control | 100% | February 15, 2025 | December 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure - Construction of Dubduban River Control (Phase 2), San Agustin, Romblon24EH0111Flood control | 100% | March 10, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Budiong River (Phase 2), Odiongan, Romblon22EH0017Flood control | 100% | September 21, 2022 | August 1, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Limon Sur (Phase 1), Looc, Romblon24EH0108Flood control | 100% | March 3, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Limon Sur (Phase 2), Looc, Romblon24EH0109Flood control | 100% | March 3, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Panique River (Phase 2), Odiongan, Romblon22EH0006Flood control | 100% | September 21, 2022 | September 21, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure, Dubduban River, Package 2, San Agustin, Romblon24EH0110Flood control | 100% | March 13, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structures and Drainage Systems - Construction of Carmen Shore Protection/Causeway, San Agustin, Romblon Phase 323EH0100Flood control | 100% | April 21, 2024 | February 29, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Gabawan River Control along Bulwang Upstream (B/S) Phase 2, Odiongan Romblon24EH0064Flood control | 100% | March 7, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Gabawan River Control along Bulwang-Upstream(B/S) Phase 3, Odiongan, Romblon24EH0065Flood control | 100% | March 7, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Ilaya Buli River Control, Sitio Ilaya, Brgy. Buli, San Agustin, Romblon24EH0087Flood control | 100% | February 15, 2025 | November 15, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Mainit (DS - LS), Flood Control Structure, Odiongan, Romblon24EH0080Flood control | 100% | March 4, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Mainit (DS - RS ) Flood Control Structure, Odiongan, Romblon24EH0081Flood control | 100% | March 7, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of River Control at Mayor River, Binonga-an, San Agustin, Romblon24EH0072Flood control | 100% | February 15, 2025 | November 15, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Seawall along Agutay, Magdiwang, Romblon23EH0062Flood control | 100% | March 1, 2024 | December 6, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Seawall at Poblacion, Looc, Romblon21EH0093Flood control | 100% | August 6, 2022 | July 7, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Shore Protection/Causeway/Breakwater along Bachawan Feeder Port, San Agustin, Romblon24EH0088Flood control | 100% | April 9, 2025 | November 15, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Bachawan (I - Laya) Bank Slope Protection along Tablas Circumferential Road, San Agustin, Romblon (Phase 2)22EH0153 | 100% | August 16, 2023 | June 17, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Banton Poblacion Shore Protection / Causeway Extension, Banton, Romblon22EH0042 | 100% | October 16, 2022 | October 25, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Bariri Slope Protection Structure (Phase II), Sitio Bariri, Hinag-oman, Ferrol, Romblon22EH0018 | 100% | September 21, 2022 | September 21, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Rule Definition
Share of contract value by contractor within DEO or province; flags top share > 40% or elevated HHI.
Triggering Data & citations
Contractor holds a large share of flood-control contract value in its district/province
{
"hhi": 0.2101175209169459,
"scope": "deo",
"bucketKey": "deo:Romblon District Engineering Office",
"contractor": "SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP",
"thresholds": {
"share": 0.25,
"minContracts": 3,
"minBucketContracts": 10
},
"bucketTotalPhp": 6159336809.09,
"contractorShare": 0.38857006895091334,
"contractorTotalPhp": 2393333928.6,
"contractorContracts": 26
}Source documents
Possible Innocent Explanations
- This may be due to the contractor's specialized expertise or a lack of other qualified bidders in the area.