Construction of Flood Mitigation Structure24EH0084

Construction of Flood Control Structure along David Bridge Upstream (L/S), Odiongan, Romblon

Construction of Flood Control Structure along David Bridge Upstream (L/S), Odiongan, Romblon is a DPWH-tracked public work in ODIONGAN (ROMBLON), ROMBLON, Region IV-B. Reported contract value: ₱125,450,000.00. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP. Figures trace to sumbong.

ODIONGAN (ROMBLON), ROMBLON, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canlumay Flood Control Structure, Odiongan, Romblon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008382

₱1,788,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0005017

₱602,194.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0018713

₱172,611.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008396

₱165,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004006

₱99,740.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱125,450,000.00

Progress

Reported complete (DPWH)

Start Date

March 13, 2024

Target End

February 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.