Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22CL0081 lists a cost of ₱49.50M, 1.03% above its Approved Budget for the Contract of ₱49.00M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a data entry error or a post-bid adjustment not reflected in the ABC field.

Public record entityConstruction of Slope Protection/Flood Control Structure along Tambak River (Upstream), Phase 6, Iba, Zambales
LocationIBA (CAPITAL) (ZAMBALES), ZAMBALES, Region IIIContract 22CL0081
Amount₱49,500,000.00101.03% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Slope Protection/Flood Control Structure along Tambak River (Upstream), Phase 6, Iba, Zambales22CL0081100%October 15, 2022December 12, 2022—completedsumbong source

Start: April 4, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Zambales 1st District Engineering Office",
  "ratio": 1.0102763341219234,
  "abcPhp": 48996495.64,
  "threshold": 0.995,
  "contractId": "22CL0081",
  "contractor": "CDC CONST & SUPPLIES",
  "contractCostPhp": 49500000
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate
  • This may be due to a data entry error or a post-bid adjustment not reflected in the ABC field.