Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23CJ0144 (₱57.19M) is recorded as completed in 73 days against 191 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.9%. This may be due to efficient project management, favorable conditions, or overestimated planning timelines.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Slope Protection with Steel Sheet Pile Foundation along Tarlac River Control Left Dike, Sta. Maria - San Bartolome Section, Tarlac (Package D)23CJ0144 | 100% | December 14, 2023 | August 18, 2023 | — | completedsumbong source |
Start: June 6, 2023 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2023-06-06T00:00:00.000Z",
"contractId": "23CJ0144",
"actualEndDate": "2023-08-18T00:00:00.000Z",
"targetEndDate": "2023-12-13T00:00:00.000Z",
"contractCostPhp": 57189172.97
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
- This may be due to efficient project management, favorable conditions, or overestimated planning timelines.