High Concurrent Workload for One Contractor
Contractor linked to many simultaneous projects or very high total value vs peers.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: CENTERWAYS CONST AND DEVELOPMENT INC holds 64 flood-control contracts worth ₱4.07B, 4.02× the 95th-percentile contractor total (₱1.01B); up to 42 ran at the same time. This is a capacity question worth examining. The contractor may have unusually high capacity or specialization in flood-control projects.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Bagtang - Maroroy Flood Control System (both sides), Daraga, Albay22FB0094Flood control | 100% | February 2, 2023 | February 2, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Bito River Flood Mitigation Structure along Brgy. Bayanihan Poblacion (District 4), San Fernando, Masbate23F00140Flood control | 100% | February 1, 2024 | May 6, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Bito River Flood Mitigation Structure along Brgy. Corbada, San Fernando, Masbate23F00141Flood control | 100% | February 2, 2024 | February 2, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Barangay Calomagon River, Bulan, Sorsogon22FL0038Flood control | 100% | March 2, 2023 | March 2, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Rangas River, Matnog, Sorsogon22FL0042Flood control | 100% | May 9, 2023 | May 9, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigating Structure along Rawis River (Downstream) and Gatbo River, Bacon District, Sorsogon City, Sorsogon22FK0021Flood control | 100% | December 21, 2022 | December 21, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Show 34 more projects in this bucket
| Construction of Flood Mitigation Project in Barangay Tabon-tabon to Barangay Sto. Domingo, Cadac-an River, Irosin, Sorsogon22FL0043Flood control | 100% | December 31, 2022 | December 31, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Brgy. Silangan Poblacion, District 2, San Fernando, Masbate23F00162Flood control | 100% | October 7, 2023 | December 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Brgy. Sta. Rosa and Brgy. Burgos, San Jacinto, Masbate23F00163Flood control | 100% | April 2, 2024 | April 2, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Managa-Naga River, Bulan, Sorsogon22F00007Flood control | 100% | May 21, 2023 | May 21, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Barangay Dominorog, Calabanga, Camarines Sur24FF0041Flood control | 100% | December 6, 2024 | October 11, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure of Malbog River Control Donwstream, Castilla, Sorsogon22FK0034Flood control | 100% | October 12, 2022 | October 12, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure, Camaligan, Camarines Sur22F00099Flood control | 100% | October 5, 2022 | October 5, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Milagrosa River Control, Castilla, Sorsogon22FK0036Flood control | 100% | February 13, 2023 | February 13, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Naga City Flood Control - Upstream, Naga City, Camarines Sur22F00068Flood control | 100% | February 14, 2023 | February 14, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Putiao River Control, Pilar Sorsogon22FK0011Flood control | 100% | November 19, 2022 | November 18, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Revetment Wall at Valencia River (Upstream Left Side), Phase 3, Alegria, Cebu24HO0080Flood control | 100% | October 15, 2024 | June 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Seawall, Sitio Dancalan, Barangay Buenavista, Bacon District, Sorsogon City, Sorsogon23FK0006Flood control | 100% | November 22, 2023 | November 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Sitio Guiwanon Shore Protection, Sitio Guiwanon, Barangay Danao, San Jacinto, Masbate21FM0037Flood control | 100% | July 25, 2022 | November 29, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Slope Protection, Brgy. Calomagon, Bulan, Sorsogon23FL0022Flood control | 100% | March 10, 2024 | March 10, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction/ Improvement of Flood Protection Measures along Mibacong River, Sorsogon City23FK0006Flood control | 100% | November 22, 2023 | November 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction/ Improvement of Flood Protection Measures along Tublijon River, Brgy. Tublijon, Sorsogon City23FK0006Flood control | 100% | November 22, 2023 | November 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction/ Rehabilitation of Flood Protection Measures along Hibago River Flood Mitigation Structure, Left Side, Downstream of Hibago Bridge, Brgy. Pinit, Ocampo, Camarines Sur23FF0008Flood control | 100% | October 20, 2023 | October 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction/ Rehabilitation of Flood Protection Measures along Hibago River Flood Mitigation Structure, Right Side, Downstream of Hibago Bridge, Brgy. Hibago, Ocampo, Camarines Sur23FF0004Flood control | 100% | September 20, 2023 | September 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction/Rehabilitation of San Rafael Storm Surge Protection, Donsol, Sorsogon22F00136Flood control | 100% | January 1, 2024 | December 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction/Rehabilitation of Sta. Cruz Storm Surge Protection, Donsol, Sorsogon22F00136Flood control | 100% | January 1, 2024 | December 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Mitigation Structure along Bito River, Brgy. Buenos Aires, San Fernando, Masbate22F00184Flood control | 100% | November 18, 2023 | November 18, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Mitigation Structure along Dorong-an River, Brgy. Bagahanglad, San Jacinto, Masbate22F00183Flood control | 100% | September 1, 2023 | September 1, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Mitigation Structure along Tutuban River, Brgy. Sta. Rosa, San Jacinto, Masbate22F00164Flood control | 100% | June 8, 2023 | June 8, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Revetment along Cadac-an River, Brgy. Macawayan Section, Irosin, Sorsogon22FL0023Flood control | 100% | January 23, 2023 | December 26, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Revetment along Managa-Naga River, Bulan, Sorsogon22F00142Flood control | 100% | April 13, 2023 | April 13, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Revetment along Tublijon River, Sorsogon City22FK0048Flood control | 100% | September 12, 2022 | September 12, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation/Improvement of Flood Mitigation at Fabrica River, Bulan, Sorsogon22FL0033Flood control | 100% | April 26, 2023 | April 26, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Dike at Valencia River (Upstream Left Side), Alegria, Cebu23HO0132 | 100% | January 24, 2024 | June 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Drainage System, Barangay Del Rosario, Bacon District, Sorsogon City, Sorsogon22FK0048 | 100% | September 12, 2022 | September 12, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure, Brgy. Sua, Camalig, Albay23FB0168 | 100% | April 23, 2024 | December 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Revetment Wall along Cadac-an River, Barangay Buenavista, Macawayan-Batang Section, Irosin, Sorsogon22FL0020 | 100% | April 1, 2023 | April 1, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Revetment Wall, Milagrosa River, Castilla, Sorsogon22FK0076 | 100% | June 22, 2023 | June 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Slope Protection at Barangay Padre Diaz, Bulan, Sorsogon22FL0022 | 100% | November 12, 2022 | November 12, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Shore Protection Structure, Sitio Busdak, Brgy. Bartolabac, San Jacinto, Masbate22F00163 | 100% | December 26, 2023 | December 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Rule Definition
Active project count and total value vs peer 95th percentile.
Triggering Data & citations
Contractor carries far more concurrent flood-control value than peers
{
"contractor": "CENTERWAYS CONST AND DEVELOPMENT INC",
"projectCount": 64,
"totalValuePhp": 4074343756.160001,
"peerP95TotalPhp": 1014143494.4100002,
"activeProjectCount": 0,
"simultaneousThreshold": 25
}Source documents
Possible Innocent Explanations
- Large national firm with many concurrent government clients
- Data groups joint ventures under one name