High Concurrent Workload for One Contractor
Contractor linked to many simultaneous projects or very high total value vs peers.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: EIGHT J'S CONST SERVICES holds 38 flood-control contracts worth ₱3.30B, 3.26× the 95th-percentile contractor total (₱1.01B); up to 22 ran at the same time. This is a capacity question worth examining. The contractor may simply be a large or highly specialized firm capable of handling many projects at once.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Show 32 more projects in this bucket
| Construction of Two (2) Pumping Stations along Navotas Coastal Dike, Phase 4, Navotas City22OA0108Flood control | 100% | May 17, 2023 | March 13, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Two (2) Pumping Stations along Navotas Coastal Dike, Phase 5, Navotas City22OA0109Flood control | 100% | May 17, 2023 | March 13, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Automatic Trash Screen & Accessories at Estero de Maypajo, Juan Luna Section, Manila22OE0001Flood control | 100% | October 17, 2022 | October 17, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Automatic Trash Screen & Horizontal Conveyor & Accessories at Estero de Vitas, Barangay 151, Manila City22OE0019Flood control | 100% | November 17, 2022 | November 17, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Automatic Trash Screen & Horizontal Conveyor at Estero de San Miguel at Nepomuceno St. (Phase III), Manila City22OE0023Flood control | 100% | April 15, 2023 | November 22, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump along Estero dela Reina, Barangay 9, (Phase II), Tondo, Manila23OE0019Flood control | 100% | July 25, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump along Estero dela Reina, CM Recto Ave., (Phase II), Tondo, Manila23OE0021Flood control | 100% | August 10, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Binondo (Phase V), Manila City23OE0033Flood control | 100% | August 9, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Binondo (Phase VI), Manila City23OE0034Flood control | 100% | August 9, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Binondo Phase IV, Manila City23OE0027Flood control | 100% | August 9, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Magdalena, La Torre St. (Package 1a), Tondo, Manila City24OE0034Flood control | 100% | July 14, 2024 | June 20, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Magdalena, La Torre St. (Package 1b), Tondo, Manila City24OE0035Flood control | 100% | July 29, 2024 | June 28, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Magdalena, Soler Section (Package 2a), Tondo, Manila City24OE0036Flood control | 100% | September 3, 2024 | June 20, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Maypajo (Phase I), Tondo, Manila City23OE0061Flood control | 100% | July 5, 2023 | July 12, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Maypajo (Phase II), Tondo, Manila City23OE0062Flood control | 100% | September 3, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Maypajo (Phase III), Tondo, Manila City23OE0063Flood control | 100% | September 3, 2023 | July 26, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero de Valencia (Phase III), Manila City23OE0040Flood control | 100% | September 3, 2023 | September 3, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero dela Reina, Phase VI, Manila City23OE0031Flood control | 100% | June 30, 2023 | June 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero dela Reina, Phase X, Tondo, Manila23OE0191Flood control | 100% | August 16, 2023 | June 23, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at Estero dela Reina, Phase XI, Tondo, Manila23OE0195Flood control | 100% | August 1, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump at P. Casal Bridge (Phase II) at Estero de San Miguel, Manila City23OE0010Flood control | 100% | October 7, 2023 | September 18, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump including Accessories along Estero de San Miguel at Nepomuceno St. (Phase II), Manila City22OE0026Flood control | 100% | April 18, 2023 | November 22, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump including Accessories at Estero de Vitas, Barangay 151, Manila City22OE0007Flood control | 100% | November 25, 2022 | November 17, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump including Retarding Basin along Estero de San Miguel at Mendiola St. (Phase I), Manila City22OE0004Flood control | 100% | April 20, 2023 | April 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump including Retarding Basin along Estero de San Miguel at Nepomuceno St. (Phase I), Manila City22OE0024Flood control | 100% | April 13, 2023 | April 13, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump including Retarding Basin at Estero de Maypajo (near Rizal avenue St.), Manila City23OE0064Flood control | 100% | September 24, 2023 | September 14, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Installation of Booster Pump including Retarding Basin at Estero de Vitas, Barangay 151, Manila City22OE0005Flood control | 100% | July 25, 2023 | July 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Luneta Pumping Station at Katigbak Parkway, Ermita, Manila City - Phase I24OH0025Flood control | 100% | August 17, 2024 | August 17, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Luneta Pumping Station at Katigbak Parkway, Ermita, Manila City - Phase II24OH0045Flood control | 100% | September 17, 2024 | September 17, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of drainage system along Various Major Roads within Zone 13 to Zone 24, Tondo, Manila City22OE0031 | 100% | April 6, 2023 | April 6, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Drainage System at Zone 41-57, Manila City22OE0030 | 100% | November 21, 2022 | October 17, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Lakandula Drainage Main, Tondo, Manila City22OE0018 | 100% | December 13, 2023 | December 13, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Rule Definition
Active project count and total value vs peer 95th percentile.
Triggering Data & citations
Contractor carries far more concurrent flood-control value than peers
{
"contractor": "EIGHT J'S CONST SERVICES",
"projectCount": 38,
"totalValuePhp": 3304670745.8200006,
"peerP95TotalPhp": 1014143494.4100002,
"activeProjectCount": 0,
"simultaneousThreshold": 25
}Source documents
Possible Innocent Explanations
- Large national firm with many concurrent government clients
- Data groups joint ventures under one name