Flood Control and Drainage19OI0160

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (INCLUDING PATHWAY), PASONG DIABLO CREEK, TRIBUTARY, BRGY. ALABANG, MUNTINLUPA CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (INCLUDING PATHWAY), PASONG DIABLO CREEK, TRIBUTARY, BRGY. ALABANG, MUNTINLUPA CITY is a DPWH-tracked public work in Las Piñas-Muntinlupa DEO, National Capital Region. Reported contract value: ₱8,871,169.00. Status: Reported complete (DPWH). Contractor on record: AARCON BUILDERS. Figures trace to dpwh.

Las Piñas-Muntinlupa DEO, National Capital Region
Region: National Capital Region

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-NCR-19-0003196 · ₱79,890 · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19OI0160 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-05-26 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Medium flood hazard · NCR, Fourth District

Based on the coordinates published with the DPWH record and NOAH file Metro Manila.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD CONTROL STRUCTURE (INCLUDING PATHWAY), PASONG DIABLO CREEK, TRIBUTARY, BRGY. ALABANG, MUNTINLUPA CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-NCR-19-0003196

₱79,890.00 · FY2019

Released to Division of Muntinlupa (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

386 projects · ₱11.2B total · 0 flags

Other projects by this contractor

DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA

Flood Control Management Cluster, Central Office

2018₱187.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - EPIFANIO DELOS SANTOS AVE (EDSA) - K0021 + (-158) - K0021 + 000, K0021 + (-229) - K0021 + (-158), K0021 + 000 - K0025 + 163

National Capital Region, National Capital Region

2024₱160.5M
Reported complete (DPWH)
No sat.

PREVENTIVE MAINTENANCE - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0015 + 985 - K0016 + 087, K0016 + 303 - K0016 + 651; MC DONALD JCT-AGUINALDO H-WAY - K0015 + 274 - K0015 + 690 AND MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K

Cavite 3rd DEO, Region IV-A

2025₱140.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0024 + 495 - K0025 + 438

Cavite 1st DEO, Region IV-A

2025₱103.9M
Reported complete (100% progress, DPWH status On-Going)

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF BACOOR FLOOD CONTROL PROJECT INCL. A PUMPING STATION, (PACKAGE A), BACOOR CITY, CAVITE

Region IV-A, Region IV-A

2019₱103.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - ASPHALT OVERLAY OF TANAY-SAMPALOC RD - K0066+100 - K0068+000, K0069+000 - K0070+443, TANAY, RIZAL

Rizal 2nd DEO, Region IV-A

2024₱98.0M
Reported complete (DPWH)
View all 386 projects →

4. Implementation

Contract Amount

₱8,871,169.00

Progress

Reported complete (DPWH)

Start Date

October 7, 2019

Target End

July 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.