Construction of Flood Mitigation Structure23EH0078

Construction of Pag-Alad Flood Mitigating Structure (Phase 2) along Parpagoha River Control, San Andres, Romblon

Construction of Pag-Alad Flood Mitigating Structure (Phase 2) along Parpagoha River Control, San Andres, Romblon is a DPWH-tracked public work in SAN ANDRES (ROMBLON), ROMBLON, Region IV-B. Reported contract value: ₱94,085,449.70. Status: Reported complete (DPWH). Contractor on record: MRRM TRADING & CONST / KPSL GEN CONTRACTOR INC. Figures trace to sumbong.

SAN ANDRES (ROMBLON), ROMBLON, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Calunacon Flood Control Structure along Tablas Circumferential Road (Phase 3), San Andres, Romblon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-23-0021873

₱657,118.00 · FY2023

Released to Caraga Regional Science High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱94,085,449.70

Progress

Reported complete (DPWH)

Start Date

March 9, 2023

Target End

February 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.