Construction of Flood Mitigation Structure22FI0024

Construction of Poblacion Balud Seawall, Balud, Masbate

Construction of Poblacion Balud Seawall, Balud, Masbate is a DPWH-tracked public work in BALUD (MASBATE), MASBATE, Region V. Reported contract value: ₱24,500,000.00. Status: Reported complete (DPWH). Contractor on record: LEGACY BSCA CONST AND SUPPLY CORP. Figures trace to sumbong.

BALUD (MASBATE), MASBATE, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱36,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Concrete Revetment at Buenavista River, Brgy. Magsaysay Uson, Masbate
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0012742

₱24,753,000.00 · FY2022

Released to Eastern Visayas Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001632

₱55,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003141

₱17,224,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006794

₱10,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

24 projects · ₱351.6M total · 0 flags

Other projects by this contractor

No sat.

CSSP- BIP- ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROADS/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDING/ FACILITIES- CONSTRUCTION OF ROAD BARANGAY TANQUE- BARANGAY TUBIGAN ROAD, PIO V. CORPUZ, MASBATE

Masbate 3rd DEO, Region V

2022₱29.7M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION/ IMPROVEMENT OF GUINOBATAN RIVER CONTROL, STA.3+801.50 - STA.3+810.00 (DOWNSTREAM), STA.3+834.70 - STA.3+934.20 (UPSTREAM, LEFT SIDE)

Masbate 2nd DEO, Region V

2022₱29.5M
Reported complete (DPWH)
No sat.

OO1: NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS, BUENAVISTA- KAWAYAN RD- K0060+539- K0061+300

Masbate 3rd DEO, Region V

2024₱25.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-BUILDING AND OTHER STRUCTURES-CONSTRUCTION OF COAST GUARD REGIONAL TRAINING CENTER, BRGY. MATAYUM, CATAINGAN, MASBATE

Masbate 3rd DEO, Region V

2021₱24.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BIP- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROAD, BRGY. CALAPAYAN TO LIBERTAD, CAWAYAN, MASBATE

Masbate 3rd DEO, Region V

2023₱19.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MAOLINGON, MANDAON,

Masbate 2nd DEO, Region V

2024₱19.6M
Past target date (DPWH On-Going)
View all 24 projects →

4. Implementation

Contract Amount

₱24,500,000.00

Progress

Reported complete (DPWH)

Start Date

February 11, 2022

Target End

July 23, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.