Roads21EH0096

CONSTRUCTION OF ODIONGAN - ALCANTARA NATIONAL ROAD, CROSS COUNTRY ROAD LEADING TO TUGDAN AIRPORT (PHASE 3), ODIONGAN, ROMBLON

CONSTRUCTION OF ODIONGAN - ALCANTARA NATIONAL ROAD, CROSS COUNTRY ROAD LEADING TO TUGDAN AIRPORT (PHASE 3), ODIONGAN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱28,949,999.44. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱2,820,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Panique (Upstream) Flood Control, Odiongan, Romblon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-21-0010496

₱148,000.00 · FY2021

Released to Mati National Comprehensive High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

738 projects · ₱73.0B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 1: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, SUBSECTION 3.2A, TACLOBAN CITY, LEYTE ; AND OTHER FIVE (5) PROJECTS

Region VIII, Region VIII

2024₱1.3B
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF STORM SURGE PROTECTION/TIDE EMBANKMENT, LEYTE

Region VIII, Region VIII

2023₱1.1B
Past target date (DPWH On-Going)
No sat.

CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY

Region VIII, Region VIII

2022₱511.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE MUMPONG RIVER, TUBAN-BATONG BUHAY, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.8M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, MUMPONG RIVER, TUBAN-STA. LUCIA, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.5M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES(OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF ROAD,MIISI-BONGA-BUYUAN-LIDONG-DARAGA,DARAGA/

Region V, Region V

2022₱288.5M
Reported complete (100% progress, DPWH status On-Going)
View all 738 projects →

4. Implementation

Contract Amount

₱28,949,999.44

Progress

Reported complete (DPWH)

Start Date

September 30, 2021

Target End

April 8, 2022

5. Audit