Rehabilitation / Major Repair of Flood Control Structure22OG0107

Rehabilitation of San Juan River (Phase VI), Quezon City

Rehabilitation of San Juan River (Phase VI), Quezon City is a DPWH-tracked public work in QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region. Reported contract value: ₱28,931,540.41. Status: Reported complete (DPWH). Contractor on record: MSB VITUG CONST. Figures trace to sumbong.

QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure, San Juan River (Phase 6), Quezon City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003130

₱960,579,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009346

₱30,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0007146

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003019

₱12,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0002496

₱244,688,407.00 · FY2022

Released to Quezon City 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

32 projects · ₱6.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG UGUIS RIVER, BRGY. UGUIS AND ALONG TIBANGRAN RIVER, BRGY. BARANGOBONG, MUNICIPALITY OF NUEVA ERA, ILOCOS NORTE

Flood Control Management Cluster, Central Office

2019₱715.1M
Past target date (DPWH On-Going)
No sat.

PASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 2 AND 3 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER UPSTREAM OF MARIKINA BRIDGE) STA. 14+100 TO STA. 15+450, LEFT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2017₱714.7M
Past target date (DPWH On-Going)
No sat.

PROPOSED MANILA BAY REHABILITATION PROGRAM (DREDGING AND DISPOSAL OF SOLID WASTE OR SLUDGE WASTE USING OCEAN-BASED METHODOLOGY INCLUDING CONSTRUCTION/EXTENSION OF THREE (3) DRAINAGE OUTFALLS)

National Capital Region, National Capital Region

2019₱502.3M
Past target date (DPWH On-Going)

CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY, DRAINAGE SYSTEM, CATBALOGAN CITY, INCLUDING ANTIAO RIVER CONTROL, SAMAR PROVINCE

Flood Control Management Cluster, Central Office

2018₱445.3M
Reported complete (DPWH)

CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY DRAINAGE SYSTEM, CATBALOGAN CITY INCLUDING ANTIAO RIVER CONTROL, SAMAR

Flood Control Management Cluster, Central Office

2016₱438.8M
Reported complete (DPWH)
No sat.

AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)-CONSTRUCTION OF PROTECTION WORKS USING GABIONS AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840 TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE II-A)-R

Flood Control Management Cluster, Central Office

2017₱363.2M
Reported complete (100% progress, DPWH status On-Going)
View all 32 projects →

4. Implementation

Contract Amount

₱28,931,540.41

Progress

Reported complete (DPWH)

Start Date

May 18, 2022

Target End

August 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.