Buildings and Facilities25K00356

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING), INTEGRATED LABORATORY SCHOOL, MSU, MARAWI CITY, LANAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING), INTEGRATED LABORATORY SCHOOL, MSU, MARAWI CITY, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱9,744,025.54. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: AL-HAYAT CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,744,025.54

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 30, 2025

Target End

August 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.