Roads19KG0086

CONCRETING OF BRGY. SUGOD FMR, BRGY. SUGOD, SND, LANAO DEL NORTE STA 0+000-STA 0+225

CONCRETING OF BRGY. SUGOD FMR, BRGY. SUGOD, SND, LANAO DEL NORTE STA 0+000-STA 0+225 is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱4,763,607.91. Status: Reported complete (DPWH). Contractor on record: AL-HAYAT CONST 44954. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,763,607.91

Progress

Reported complete (DPWH)

Start Date

January 15, 2020

Target End

March 4, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.