Buildings and Facilities24K00123

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. POBLACION, BINIDAYAN, LANAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. POBLACION, BINIDAYAN, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱4,801,515.57. Status: Reported complete (DPWH). Contractor on record: AL-HAYAT CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,801,515.57

Progress

Reported complete (DPWH)

Start Date

June 28, 2024

Target End

October 25, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.